LOD First Facility Update -- May 2010
 
  The building construction plans have been approved from the City of Phoenix. Construction has begun!!
 
.

 

Construction Progress:

7/2    
  • MPE rough in
  • A/c curbs roof hatch
  • Sanctuary trusses
  • Sancturary roof sheathing
  • Foam roofing in low areas
  • Insulation
  • Window frames
  • Foam for Stucco
 
7/16
  • Stage rough in
  • Set windows
  • Exterior headers
  • Dry in slopped roofs
  • Glazing
  • Foam roof
  • Hardscape
 

God bless this work. 